سؤال 1
[CH1] Which of the following is NOT one of the major characteristics of a project?
سؤال 2
[CH1] Which of the following activities is best classified as a project rather than routine, repetitive work?
سؤال 3
[CH1] A consumer electronics firm finds that its products now become outdated within months instead of years, so it must bring new products to market much faster. Which driver of project management does this illustrate?
سؤال 4
[CH1] A project team is currently preparing schedules and budgets, assigning staff, and identifying risks. In which stage of the project life cycle is the team?
سؤال 5
[CH1] According to the course, when Agile PM is combined with traditional methods, at which point is Agile most often used?
سؤال 6
[CH1] A project manager spends most of her week on one kind of work that the course places under the sociocultural dimension (the 'art') of project management. Which of the following is that work?
سؤال 7
[CH2] A project manager shows senior management how her project contributes to the firm's mission in order to keep their continued support. Which reason for understanding strategy does this reflect?
سؤال 8
[CH2] A project keeps getting approved at every review because a powerful senior vice-president champions it, even though the supporting data is weak. This situation is best described as:
سؤال 9
[CH2] An engineer stops working on a task for Project A to help on Project B, then later returns to the original task on Project A. Which problem of a missing priority system does this illustrate?
سؤال 10
[CH2] Which of the following shows the correct sequence of the four activities of the strategic management process?
سؤال 11
[CH2] A firm's R&D portfolio includes a project based on a technological breakthrough in battery chemistry that has tremendous commercial potential. Using the Matheson classification, this project is a:
سؤال 12
[CH2] A company approves a project with a modest net present value because it will make it difficult for competitors to enter the market. The company is relying mainly on:
سؤال 13
[CH2] Which of the following is NOT a responsibility of the governance team in managing the portfolio system?
سؤال 14
[CH4] According to the course, a work breakdown structure (WBS) is best suited to which of the following projects?
سؤال 15
[CH3] Members of a dedicated project team start referring to the rest of the company as 'them' and develop a we-they attitude toward other departments. This negative effect is known as:
سؤال 16
[CH3] Which of the following is a disadvantage of using the functional organization to complete projects?
سؤال 17
[CH3] An engineering firm's project management office mainly provides the organization with a cadre of trained project managers and professionals. This PMO is best characterized as a:
سؤال 18
[CH3] Which of the following best describes matrix management?
سؤال 19
[CH3] A consultant trying to understand a company's culture examines its office layout, how parking spaces are allocated, and the design of its headquarters building. Which method of identifying cultural characteristics is she using?
سؤال 20
[CH3] When choosing a project management structure, which of the following is a project consideration rather than an organization consideration?
سؤال 21
[CH4] An airport renovation contract states that the crew may work inside the terminal only between midnight and 5:00 a.m., and that repair work is included only up to one month after final inspection. Which element of the project scope checklist do these statements represent?
سؤال 22
[CH4] Which document authorizes the project manager to initiate and lead the project, and often includes items such as risk limits, the business case, and spending limits?
سؤال 23
[CH4] During a software project, developers add an animated dashboard that the client never requested because they believe users will like it. Which cause of scope creep is this?
سؤال 24
[CH4] A product launch must happen on the date of a fixed trade show, the budget should be kept as low as possible, and some features may be dropped if necessary. In the priority matrix, how should time be classified?
سؤال 25
[CH4] In integrating the WBS with the organization, what is created at the intersection of a work package and an organization unit?